Timeline

Sep 2021
RDRP commences
Oct 2022
Nine additional regions commence RDRP
Sep 2023
Five pilot regions publish RDRPs
Sep 2024
Implementation Phase 1 commences
Dec 2025
Nine regions finalise their RDRPs
Jul 2026
Implementation Phase 2 opens
Aug 2026
Implementation Phase 2  Round 1 commences
Nov 2026
Implementation Phase 1 activities complete
Feb 2027
Implementation Phase 1 acquittal complete
Jun 2029
Implementation Phase 2 activities complete
Sep 2029
Implementation Phase 2 acquittal complete

Funding Rounds

Process and timeframes for lodgment, assessment and approval of draft Eligibility Notices. Once your Eligibility Notice is approved, applicants can apply for financial assistance via QRIDA.QRIDA
RoundsApplications due from regions on draft Eligibility Notices by:Pre-assessment and CDOC[1] endorsement. Region advised of ‘in-principle’ approval by:Chief Executive approvalsApplications to QRIDA for funding with final Eligibility Notices
114 August 2026

Remuneration grant activities only*
By end September 2026 By end October 2026Applications made by the regional entities following receipt of the final Eligibility Notice by the Chief Executive (Director-General, Department of Primary Industries)
215 September 2026By end October 2026By end November 2026
315 January 2027By end February 2027By end March 2027
415 March 2027By end April 2027By end May 2027
514 May 2027By end June 2027By end July 2027
615 July 2027By end August 2027By end September 2027
715 September 2027By end October 2027By end November 2027
814 January 2028By end February 2028By end March 2028
915 March 2028By end April 2028By end May 2028
1015 May 2028By end June 2028By end July 2028
1114 July 2028By end August 2028By end September 2028
1215 September 2028By end October 2028By end November 2028
1315 January 2029By end February 2029By end March 2029

Phase 2 implementation completed by Friday, 29 June 2029.

Phase 2 acquittal period (administrative close out activities with QRIDA) completed by Friday, 28 September 2029.

[1] Climate and Drought Oversight Committee

*Round 1 remuneration grant application due date allows for continuity of Implementation Officer engagement from Phase 1 to Phase 2, factoring in assessment and approval timeframes. Remuneration grants can still be lodged in future rounds, with consideration of the assessment and approval timeframes.